MANAGEMENT – 2015: Daily Answer Writing Challenge – 25
- job shop incurs different costs per day, for processing 5 different jobs in the shop on a single machine. All jobs are available at time t = 0. The data for the jobs is given below Draw Gantt chart for SPT rule, slack time sequence rule, to compute average tardiness and lateness for each of the above rules.
| JOB | PROCESSING | DUE DATES |
| 1 | 5 | 13 |
| 2 | 3 | 15 |
| 3 | 7 | 22 |
| 4 | 2 | 9 |
| 5 | 4 | 7 |